Hayes | James performed planning, permitting, surveying, engineering design and construction administration for a 400,000 gallon elevated water storage tank, 10,824 feet of 8-inch water line and 35,376 feet of 16-inch water line. The purpose of this project was to provide drinking water and fire protection for a regional solid waste processing plant being built near Arabi.
Hayes | James also assisted Arabi in upgrading its groundwater wells to meet the needs of the new industrial demand. The major portion of the financing for this project came from EDA, (Economic Development Administration) because of the large number of jobs created at the solid waste processing facility. The other portion came from the financing of the solid waste processing facility. GEFA provided construction financing.